Chapter 13 of CSI Project Delivery Practice Guide (PDPG) continues with an overview of Construction, which are on the Construction Documents Technologists (CDT) Exam. This is a general summary of key terms and concepts. A more detailed resource is the CSI Construction Contract Administration Practice Guide, which is also a reference for another CSI certification exam, Certified Construction Contact Administration (CCCA).
There are two main categories:
-
Construction Contract Administration (CCA)
-
Construction Project Management (CPM)
Construction as Team Activity
Responsibility for oversight is with the architect/engineer (A/E After providing design services, the A/E usually continues to represent the owner during the construction stage.
-
Team Approach
Know the benefits and obstacles to working as a team. Also understand the importance of team building and collaborative effort.
-
Understanding the Documents
-
Contract Documents
-
Agreement
-
Conditions of Contract
-
Addenda affecting contract documents
-
Contract modifications, such as change orders and change directives
-
Drawings
-
Specifications
-
Drawings - Know types and which information is best shown in drawings, instead of specifications.
-
Specifications
-
Administering Construction Based on Delivery Methods
Again, just have basic understanding of this per project delivery method.
-
Roles and Responsibilties
Know what is required of different participants during the construction process.
-
Owner
-
Architect/Engineer
-
Contractor
-
Subcontractors and Suppliers
-
Consultants
-
Authorities Having Jurisdiction
-
Testing Agency Inspectors
-
Commissioning Authority
-
Product Representatives
-
Communication
-
Oral and Written Communication
-
Electronic Communication
Preconstruction
-
Contractor's Organization
-
Award of Subcontractors
-
Purchase Orders
-
Notice to Proceed (NTP)
-
Contract Documents
-
Preconstruction Submittals
-
Permits and Regulatory Issues
-
Preconstruction Meetings
-
Verification of Site Conditions
-
Mobilization - typically occurs after receipt of NTP and following proconstruction and site mobilization meetings
Meetings
Know basics of effective meetings - purpose, agenda, and time limit (PAL)
-
Procedures and Administration
These are typically defined in Division 01 of specifications, although additional requirements for meetings may be in Divisions 02-49.
-
Types of Meetings
Submittals
-
Contract Documents - outlines administrative and procedural requirements
-
Preconstruction Submittals
-
Construction Submittals
-
Action Submittals
-
Product Data
-
Shop Drawings
-
Samples
-
Informational Submittals
-
Coordination drawings
-
Certificates
-
Design and delegated design data
-
Test and evaluation reports
-
Manufacturer's instructions
-
Manufacturer's reports
-
Sustainable design reports
-
Qualitifcation statements
-
Construction photographs
-
Closeout and Maintenance Submittals
-
O&M data
-
Bonds
-
Special warranties
-
Record documents (shop drawings, record drawings and specifications, addenda, change orders, field orders, photographs)
-
Spare parts and materials (aka "attic stock")
-
Keying
-
Submittal Preparation
-
Submittal Review
-
Participant Responsibilities
Know the different responsibilities for subcontractors and suppliers, contractor, A/E, consultants, and owner.
-
Record Keeping
Submittal log should be maintained by both the A/E and the contractor.
-
Processing Procedures
Complete, accurate, and timely
Site Visits, Observations, and Inspections
Review PDPG - Chapter 13, pages 409-415.
Quality Assurance and Quality Control
Know definition of QA and QC and when each occurs on the project process.
Interpretations and Modifications
-
Interpreting Contract Documents
-
Contract Document Relationships
-
Requests for Interpretations (RFI)
-
Contract Modifications
-
Construction Change Process and Documentation
-
Written requests for change (not a directive to make a change) - proposal request, change order request, request for substitutions
-
Minor changes, change directives, and change orders
-
Minor Changes - those which do not affect contract sum or time
-
Architect's supplemental instructions (AIA)
-
Field Order (EJCDC)
-
Writtern interpretation or clarifications (EJCDC)
-
Change Directives - directs change to be made
-
Construction change directive (AIA)
-
Work change directive (EJCDC)
-
Change Orders
-
Substitutions
-
Feedback
Executing Work
Claims and Disputes
Measurement and Payment
Project Closeout
Image Credit: Getty Images (RedChopsticks)